Modernisation of Permskaya GRES
conventional generation
construction
industrial automation
completed
Works
Modernisation of the complete switchgear, technical re-equipment of relay protection and automation, reconstruction of the piping system of the block desalting plant.
Parameters
Description
Project geography
Dobryanka
Companies
MashTekhStroy, EnergoSet
Work type
Construction of buildings and its systems, Installation of machinery, equipment and communications, Industrial automation
Customer
Inter RAO
Status
Completed