build

Power Supply to Zaryadye Park

distribution lines

construction

completed

Works

Construction of five transformer substations with voltage classes 220 kV, 20 kV and 10 kV, construction of 20 kV and 0.4 kV cable lines.

Parameters

Description

Project geography

Moscow

Companies

NPK KhimStroyEnergo

Work type

Construction of buildings and its systems, Installation of machinery, equipment and communications

Customer

ROSSETI

Status

Completed